Elizabeth Line in London begins operation – Bauer substantially involved in the construction of three stations

London, UK – After multiple years of construction and an extensive period of trial operation, it's finally time: On May 24 London's Elizabeth line (formerly Crossrail) was formally opened. The Elizabeth line will increase central London’s rail capacity by 10 per cent and is more than 100 km long with new trains operating in 42 km of new tunnel and track under central London, connecting 41 stations and bringing an additional 1.5 million people within 45 minutes of London. BAUER Technologies Ltd., the UK subsidiary of BAUER Spezialtiefbau GmbH, was substantially involved in the foundations for the enabling work packages for three stations: Tottenham Court Road station, Moorgate shaft at Liverpool Street Station and Whitechapel Station.

In December 2009, the joint venture Bauer Keller was awarded the contract to carry out the foundation work as part of Tottenham Court Road Station project which included structures for both London Underground and Crossrail. The work was executed from April 2010 to September 2011 and included the construction of 10,000 m2 of secant pile wall, 6,437 m2 of diaphragm wall and seven permanently cased piles of varying lengths, diameters and levels of difficulty.

The largest casing diameter was 2.43 m, while the largest drilling diameter was 2.03 m. The deepest pile was installed at a depth of 64 m. A BAUER BG 40 and a BG 28 were used. One particular challenge was the extremely cramped spatial conditions: after all, the construction site was in the centre of London. In addition, pile construction in the immediate vicinity of operational tunnels for the Northern line required the Bauer team to rely on many years of expertise and sharp intuition, including a real first in that one of the permanently cased piles had to be partially (i.e. to a depth of 36 m) constructed in a D-shape, due to an adjacent escalator box structure.

In February 2012 Bauer began foundation work on Moorgate Shaft at Liverpool Street Station. Before the main piling work could start, Bauer first had to remove 25 existing piles, which were 34 m deep, with a maximum diameter of 1350 mm, which included the removal of two existing piles with permanent steel liners. The challenge here was not only the spatial restrictions in the centre of London's financial district, but also the strict noise control regulations on the site. On top of this, it was necessary to minimize vibrations and any resulting disruptive effects on underlying subway tunnels, pipework or adjacent buildings.

The core of the specialist foundation engineering work for the Moorgate Shaft was the construction of a 60 m deep shaft. The required diaphragm wall elements, up to a depth of 53 m, were constructed using a BAUER MC 64 duty-cycle crane equipped with a grab. In addition, Bauer constructed three 60 m deep piles with a diameter of 2.4 m for the subsequent above-ground buildings as well as eight barrette piles up to a depth of 60 m. In August 2013, the team from Bauer Technologies completed their work on the Liverpool Street’s Moorgate Shaft.

In February 2012, Bauer also began foundation work for the Whitechapel Station upgrade project. Here as well, extremely tight working spaces and access options made the project a complicated logistical puzzle. By May 2013, Bauer had constructed a total of 13,000 m2 of diaphragm wall and barrette piles to a depth of up to 51 m for two shafts. Among other equipment, a BAUER MC 64 duty-cycle crane with grab was used for this work. Connecting the complex reinforcement cages and installing the large volumes of concrete that were required for each diaphragm wall element posed a major challenge.

In February 2012, Bauer also began foundation work for the Whitechapel Station upgrade project. Here as well, extremely tight working spaces and access options made the project a complicated logistical puzzle. By May 2013, Bauer had constructed a total of 13,000 m2 of diaphragm wall and barrette piles to a depth of up to 51 m for two shafts. Among other equipment, a BAUER MC 64 duty-cycle crane with grab was used for this work. Connecting the complex reinforcement cages and installing the large volumes of concrete that were required for each diaphragm wall element posed a major challenge.

"We are delighted to have been able to make a contribution to what is currently the most significant infrastructure project in London", says Michael Jones, Managing Director of BAUER Technologies Ltd.

More information on the opening of the Elizabeth Line can also be found at https://tfl.gov.uk/.

 

Downloads

Your Contact

Martina Krammer
Marketing & Communications Manager

Specialized Press Geotechnical Solutions